Museum renovation
  • Location: Jerusalem
  • Client: Israel Museum
  • Period: 2008
  • Budget: $6 million
  • Area:
    25,000m2
  • Description:

    Work on the air conditioning system, installation of a centrifugal water chiller in the energy center (capacity of 1,000 refrigeration tons) along with all related systems (pumps, heating furnaces), along with renovation of chiller towers and switchboards. New HVAC systems were installed in 24 machine rooms to ensure consistent temperature and humidity levels in exhibition halls. The project was completed while air conditioning systems were still running in the sections of the museum that were open to the public. 